As you already know, Canton Township will be performing road work in your subdivision this year. Heather Gendron from Spalding DeDecker is the Project Manager again this year and will also be providing updates throughout construction. She will be your first point of contact for day-to-day construction matters, but as always, Charles Larocque and myself in Engineering Services are always available as well.
Cipparrone Contracting Inc. is the Contractor performing the work this year.
They have provided the following tentative construction schedule based on zones or areas:
Stage 1 – June 1 to July 5
Stage 2 – July 6 to September 3
Stage 3 – September 4 to October 18
Stage 1 Subdivisions:
Brookside 5
Century Farms
Franklin Palmer
Nowland Estates
River Park
Stonegate Oakvale
Stage 2 Subdivisions:
Central Park 1
Fairways West
Glengarry 1
Glengarry 3
KIrkway
Pinewood
Stage 3 Subdivisions:
Mayfair Village
Northpoint
Stratford Park
Willow Creek (Willow Homes)
Wilshire Estates
Windsor Park
Please note concrete must cure for about 5 days before it can be open to traffic, an adjacent panel can be removed, or asphalt work can occur next to it.
As work is approaching in your sub please notify your residents if you have the ability to do so.
Please give them the following information and reminders:
Mark T. Merkey
Staff Engineer II
Engineering Services
Canton Township
1150 S. Canton Center Rd.
Canton Michigan 48188
Office: 734-394-5142
www.canton-mi.org
Cipparrone Contracting Inc. is the Contractor performing the work this year.
They have provided the following tentative construction schedule based on zones or areas:
Stage 1 – June 1 to July 5
Stage 2 – July 6 to September 3
Stage 3 – September 4 to October 18
Stage 1 Subdivisions:
Brookside 5
Century Farms
Franklin Palmer
Nowland Estates
River Park
Stonegate Oakvale
Stage 2 Subdivisions:
Central Park 1
Fairways West
Glengarry 1
Glengarry 3
KIrkway
Pinewood
Stage 3 Subdivisions:
Mayfair Village
Northpoint
Stratford Park
Willow Creek (Willow Homes)
Wilshire Estates
Windsor Park
Please note concrete must cure for about 5 days before it can be open to traffic, an adjacent panel can be removed, or asphalt work can occur next to it.
As work is approaching in your sub please notify your residents if you have the ability to do so.
Please give them the following information and reminders:
- Please ask residents to park in drives instead of the street during construction, or park a good distance from the pavement improvements. They will be asked to move vehicles if they are in the way. A few days before the contractor starts, a Spalding DeDecker inspector will paint the limits of repairs, then barrels will be dropped off by the Contractor so residents will know if they are affected.
- Please ask that they have their lawn sprinkler systems turned off while work is occurring in front of their homes. The excess water can make the work more difficult for the contractor, especially if it is filling open holes in the pavement.
- Tell residents not to drive through the concrete slurry that results from saw cutting concrete as it can make a mess of cars when splashed and is very difficult to get off. The same is true of tack for asphalt roads - please tell them not to drive on milled, tacked surfaces as the tack can coat tires and is very difficult to remove if it gets on cars.
- In the event of limited access to mail boxes, know that the USPS will hold mail at the post office if they cannot get to mail boxes.
- The contractor will assist in getting trash receptacles picked up at the end of the drive on trash day if driveways are blocked due to construction. This requires residents to have their trash out to the curb in a timely manner.
- Lastly, please remind residents that we understand the construction work may be inconvenient, but bear with us as we do the work and we will try to minimize the disruption and the time we are in each sub. Please slow down when going through construction areas since there may be workers present, or it may be down to 1 lane and you need to watch for oncoming traffic.